Residences Refurbishment Programme
Contractor: Various
Start Date: May 2009
Contract Completion Date: September 2009
Value: £2.9m
Scope of Works:
The Minor Works Team have been asked to undertake a variety of refurbishment projects this summer, including:
- Aberconway Hall: Flats A-H
- Cartwright Court: Houses 11-14
- Colum Road: Houses 124, 130, 146 & 152
- Gordon Hall: Ground Floor
- Senghenydd Court: Blocks A-K Fire Alarms
- Senghenydd Court: Block H
- Talybont South: Houses 19, 17 & 13
- Talybont North: Block M & Southgate House
- University Hall: Nevern 2 & Wardens
- Village Houses: 10, 12 & 26 Ruthin Gardens, 46 & 64 Miskin Street and 10 Llandough Street